6 turbines · operational · Strathclyde
| Status | Operational |
|---|---|
| County / region | Strathclyde |
| Turbines | 6 |
| Installed capacity | 12 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Scottish Power Renewables |
| Turbine manufacturer | Siemens Gamesa |
| Turbine model | G80 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3702.
The application was determined in about 42 months. Construction to first power took about 16 months. The scheme has been operating for about 13 years. That works out at 2 MW per turbine on average.
See all wind farms in Strathclyde.