6 turbines · operational · Highland
| Status | Operational |
|---|---|
| County / region | Highland |
| Turbines | 6 |
| Installed capacity | 15 MW |
| Turbine capacity | 2.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | West Coast Energy Ltd/Falck Renewables |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 2 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2723.
The application was determined in about 7 months. Construction to first power took about 12 months. The scheme has been operating for about 15 years. That works out at 2.5 MW per turbine on average.
See all wind farms in Highland.