Millennium Extension II

6 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines6
Installed capacity15 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)West Coast Energy Ltd/Falck Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 Project timeline Application submitted January 2009 Permission granted August 2009 Under construction April 2010 Operational April 2011

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2723.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 12 months. The scheme has been operating for about 15 years. That works out at 2.5 MW per turbine on average.