16 turbines · operational · Highland
| Status | Operational |
|---|---|
| County / region | Highland |
| Turbines | 16 |
| Installed capacity | 40 MW |
| Turbine capacity | 2.5 MW |
| Tip height | 125 m |
| Operator (or applicant) | Renewable Development Company (RDC) Scotland (Ltd) for FALCK RENEWABLES |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
The register links a second scheme on this site (REPD ref 3598, Operational): 4 turbines · 2.5 MW each · 125 m tip height · applicant West Coast Energy /Falck Renewables. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4682.
The application was determined in about 16 months. Construction to first power took about 25 months. The scheme has been operating for about 18 years. That works out at 2.5 MW per turbine on average.
See all wind farms in Highland.