Millour Hill Community Windfarm (Extension)

6 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines6
Installed capacity18 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Community Windpower
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Scheme REPD 3690 Application submitted June 2009 Permission granted December 2009 Under construction April 2011 Operational May 2012 Permission expired December 2015 Scheme REPD 4235 Permission expired June 2011 Application submitted November 2013 Permission granted June 2014 Under construction January 2016 Operational March 2016

From application to operation, this scheme took about 3 years.

The register links a second scheme on this site (REPD ref 4235, Operational): 2 turbines · 3.2 MW each · applicant Community Windpower. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3690.

What the register tells us

The application was determined in about 6 months. Construction to first power took about 13 months. A planning permission on this site expired in December 2015. The scheme has been operating for about 14 years. That works out at 3 MW per turbine on average.