Milton of Fisherie Wind Cluster

2 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines2
Installed capacity4.6 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)LocoGen
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted May 2011 Permission granted November 2012 Under construction April 2015 Permission expired November 2015 Operational February 2016

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3809.

What the register tells us

The application was determined in about 18 months. Construction to first power took about 10 months. A planning permission on this site expired in November 2015. The scheme has been operating for about 10 years. That works out at 2.3 MW per turbine on average.