3 turbines · operational · Western Isles
| Status | Operational |
|---|---|
| County / region | Western Isles |
| Turbines | 3 |
| Installed capacity | 1.5 MW |
| Turbine capacity | 0.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | North Harris Trust |
| Turbine manufacturer | WindFlow |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 9 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4629.
The application was determined in about 21 months. Construction to first power took about 8 months. A planning permission on this site expired in February 2011. The scheme has been operating for about 11 years. That works out at 0.5 MW per turbine on average.