Mossmorran Wind Farm

2 turbines · operational · Fife

Wind farm facts

StatusOperational
County / regionFife
Turbines2
Installed capacity4.6 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Airvolution Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 Scheme REPD 2780 Permission expired January 2011 Application submitted April 2011 Permission granted January 2012 Under construction September 2015 Operational December 2015 Scheme REPD 3889 Application submitted June 2012

From application to operation, this scheme took about 4 years.

The register links a second scheme on this site (REPD ref 3889, Application Withdrawn): 2 turbines · 3 MW each · applicant Airvolution Energy. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2780.

What the register tells us

The application was determined in about 9 months. Construction to first power took about 3 months. A planning permission on this site expired in January 2011. The scheme has been operating for about 11 years. That works out at 2.3 MW per turbine on average.

Nearby

See all wind farms in Fife.