Moy Wind Farm (2nd Application)

20 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines20
Installed capacity66 MW
Turbine capacity3.3 MW
Tip heightnot recorded
Operator (or applicant)Eneco
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2012 2013 2014 2015 2016 2017 Project timeline Application submitted April 2013 Permission granted January 2014 Under construction April 2014 Operational May 2016

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3647.

What the register tells us

The application was determined in about 9 months. Construction to first power took about 25 months. The scheme has been operating for about 10 years. That works out at 3.3 MW per turbine on average.