Muirake

2 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines2
Installed capacity4.6 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Vento Ludens
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 Project timeline Application submitted November 2009 Permission granted September 2010 Operational December 2011 Permission expired September 2012

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3594.

What the register tells us

The application was determined in about 10 months. A planning permission on this site expired in September 2012. The scheme has been operating for about 15 years. That works out at 2.3 MW per turbine on average.