Muirhall South

3 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines3
Installed capacity8.3 MW
Turbine capacity3.2 MW
Tip height147 m
Operator (or applicant)Muirhall Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted March 2014 Refused November 2014 Permission granted July 2015 Granted on appeal July 2015 Under construction January 2016 Operational March 2016 Permission expired July 2018

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4281.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 2 months. The register records a refusal in November 2014 before the scheme progressed. Permission was ultimately granted on appeal in July 2015. A planning permission on this site expired in July 2018. The scheme has been operating for about 10 years. That works out at 2.77 MW per turbine on average.