4 turbines · operational · Neath Port Talbot
| Status | Operational |
|---|---|
| County / region | Neath Port Talbot |
| Turbines | 4 |
| Installed capacity | 8 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | REG Windpower |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4193.
The application was determined in about 35 months. Construction to first power took about 11 months. Permission was ultimately granted on appeal in July 2015. A planning permission on this site expired in July 2020. The scheme has been operating for about 9 years. That works out at 2 MW per turbine on average.