Mynydd Brombil Wind Farm

4 turbines · operational · Neath Port Talbot

Wind farm facts

StatusOperational
County / regionNeath Port Talbot
Turbines4
Installed capacity8 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)REG Windpower
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 Project timeline Application submitted August 2012 Permission granted July 2015 Granted on appeal July 2015 Under construction February 2016 Operational January 2017 Permission expired July 2020

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4193.

What the register tells us

The application was determined in about 35 months. Construction to first power took about 11 months. Permission was ultimately granted on appeal in July 2015. A planning permission on this site expired in July 2020. The scheme has been operating for about 9 years. That works out at 2 MW per turbine on average.