9 turbines · operational · Mid Glamorgan
| Status | Operational |
|---|---|
| County / region | Mid Glamorgan |
| Turbines | 9 |
| Installed capacity | 22.5 MW |
| Turbine capacity | 2.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | Pennant Walters |
| Turbine manufacturer | Nordex |
| Turbine model | N90/2500 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 6 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3705.
The application was determined in about 37 months. Construction to first power took about 15 months. The register records a refusal in May 2011 before the scheme progressed. Permission was ultimately granted on appeal in June 2012. A planning permission on this site expired in June 2012. The scheme has been operating for about 11 years. That works out at 2.5 MW per turbine on average.