Mynydd Bwllfa Wind Farm - Resubmission

9 turbines · operational · Mid Glamorgan

Wind farm facts

StatusOperational
County / regionMid Glamorgan
Turbines9
Installed capacity22.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Pennant Walters
Turbine manufacturerNordex
Turbine modelN90/2500

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted May 2009 Refused May 2011 Permission granted June 2012 Granted on appeal June 2012 Permission expired June 2012 Under construction February 2014 Operational May 2015

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3705.

What the register tells us

The application was determined in about 37 months. Construction to first power took about 15 months. The register records a refusal in May 2011 before the scheme progressed. Permission was ultimately granted on appeal in June 2012. A planning permission on this site expired in June 2012. The scheme has been operating for about 11 years. That works out at 2.5 MW per turbine on average.