Myres Hill

2 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines2
Installed capacity1.8 MW
Turbine capacity0.9 MW
Tip heightnot recorded
Operator (or applicant)National Energy Laboratories (NEL)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1998 1999 2000 2001 2002 Project timeline Application submitted May 1999 Permission granted August 2001 Operational November 2001

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3090.

What the register tells us

The application was determined in about 27 months. The scheme has been operating for about 25 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.9 MW per turbine on average.