Myreton Crossroads

2 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines2
Installed capacity1.6 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)Seren Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Project timeline Application submitted February 2009 Refused December 2009 Permission granted July 2010 Granted on appeal July 2010 Under construction March 2012 Operational July 2013 Permission expired July 2019

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3804.

What the register tells us

The application was determined in about 17 months. Construction to first power took about 16 months. The register records a refusal in December 2009 before the scheme progressed. Permission was ultimately granted on appeal in July 2010. A planning permission on this site expired in July 2019. The scheme has been operating for about 13 years. That works out at 0.8 MW per turbine on average.