Nash Waste Water Treatment Works Turbine

1 turbines · operational · Gwent

Wind farm facts

StatusOperational
County / regionGwent
Turbines1
Installed capacity2.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Welsh Water
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted December 2011 Permission granted July 2012 Under construction February 2017 Operational March 2017 Permission expired July 2018

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3887.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 1 month. A planning permission on this site expired in July 2018. The scheme has been operating for about 9 years. That works out at 2.5 MW per turbine on average.