Nethercott Farm

3 turbines · operational · Devon

Wind farm facts

StatusOperational
County / regionDevon
Turbines3
Installed capacity1.5 MW
Turbine capacity0.5 MW
Tip heightnot recorded
Operator (or applicant)Private Developer
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2013 2014 2015 2016 2017 2018 Project timeline Application submitted January 2014 Permission granted July 2014 Under construction August 2016 Operational December 2016 Permission expired July 2017

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3368.

What the register tells us

The application was determined in about 6 months. Construction to first power took about 4 months. A planning permission on this site expired in July 2017. The scheme has been operating for about 10 years. That works out at 0.5 MW per turbine on average.

Nearby

See all wind farms in Devon.