New Albion Wind Farm

7 turbines · operational · Northamptonshire

Wind farm facts

StatusOperational
County / regionNorthamptonshire
Turbines7
Installed capacity14.4 MW
Turbine capacity2.05 MW
Tip heightnot recorded
Operator (or applicant)John Laing Environmental Assets Group
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted August 2009 Permission granted January 2010 Permission expired January 2010 Under construction January 2015 Operational January 2016

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4513.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 12 months. A planning permission on this site expired in January 2010. The scheme has been operating for about 10 years. That works out at 2.06 MW per turbine on average.