New Barn Farm

3 turbines · operational · Lancashire

Wind farm facts

StatusOperational
County / regionLancashire
Turbines3
Installed capacity4.5 MW
Turbine capacity1.5 MW
Tip heightnot recorded
Operator (or applicant)Private Developer
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 Project timeline Application submitted September 2002 Refused March 2003 Permission granted February 2004 Granted on appeal February 2004 Under construction October 2006 Operational February 2007 Permission expired February 2012

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4685.

What the register tells us

The application was determined in about 17 months. Construction to first power took about 4 months. The register records a refusal in March 2003 before the scheme progressed. Permission was ultimately granted on appeal in February 2004. A planning permission on this site expired in February 2012. The scheme has been operating for about 19 years. That works out at 1.5 MW per turbine on average.

Nearby