Newstead and Annesley Wind Turbine

1 turbines · operational · Nottinghamshire

Wind farm facts

StatusOperational
County / regionNottinghamshire
Turbines1
Installed capacity1.5 MW
Turbine capacity1.5 MW
Tip height126 m
Operator (or applicant)Redpath Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted October 2014 Permission granted October 2015 Under construction August 2016 Operational December 2016 Permission expired October 2018

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4917.

What the register tells us

The application was determined in about 12 months. Construction to first power took about 4 months. A planning permission on this site expired in October 2018. The scheme has been operating for about 10 years. That works out at 1.5 MW per turbine on average.