Newthorpe Wind Turbine

1 turbines · operational · Nottinghamshire

Wind farm facts

StatusOperational
County / regionNottinghamshire
Turbines1
Installed capacity2.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Severn Trent Water
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted December 2010 Permission granted July 2011 Under construction April 2013 Operational April 2014

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3793.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 12 months. The scheme has been operating for about 12 years. That works out at 2.5 MW per turbine on average.