Newton Down

2 turbines · operational · Mid Glamorgan

Wind farm facts

StatusOperational
County / regionMid Glamorgan
Turbines2
Installed capacity5 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Partnerships Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted May 2012 Refused July 2012 Permission granted May 2013 Granted on appeal May 2013 Under construction April 2016 Operational September 2016

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3904.

What the register tells us

The application was determined in about 12 months. Construction to first power took about 5 months. The register records a refusal in July 2012 before the scheme progressed. Permission was ultimately granted on appeal in May 2013. The scheme has been operating for about 10 years. That works out at 2.5 MW per turbine on average.