2 turbines · operational · Mid Glamorgan
| Status | Operational |
|---|---|
| County / region | Mid Glamorgan |
| Turbines | 2 |
| Installed capacity | 5 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Renewable Energy Partnerships Ltd |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 4 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3904.
The application was determined in about 12 months. Construction to first power took about 5 months. The register records a refusal in July 2012 before the scheme progressed. Permission was ultimately granted on appeal in May 2013. The scheme has been operating for about 10 years. That works out at 2.5 MW per turbine on average.