2 turbines · operational · Lincolnshire
| Status | Operational |
|---|---|
| County / region | Lincolnshire |
| Turbines | 2 |
| Installed capacity | 4.6 MW |
| Turbine capacity | 2.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | TCI Renewables |
| Turbine manufacturer | Enercon |
| Turbine model | E70 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 6 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3827.
The application was determined in about 16 months. Construction to first power took about 22 months. The register records a refusal in May 2008 before the scheme progressed. Permission was ultimately granted on appeal in May 2009. A planning permission on this site expired in May 2019. The scheme has been operating for about 12 years. That works out at 2.3 MW per turbine on average.