Newton Marsh Wind Project

2 turbines · operational · Lincolnshire

Wind farm facts

StatusOperational
County / regionLincolnshire
Turbines2
Installed capacity4.6 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)TCI Renewables
Turbine manufacturerEnercon
Turbine modelE70

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Project timeline Application submitted January 2008 Refused May 2008 Permission granted May 2009 Granted on appeal May 2009 Under construction June 2012 Operational April 2014 Permission expired May 2019

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3827.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 22 months. The register records a refusal in May 2008 before the scheme progressed. Permission was ultimately granted on appeal in May 2009. A planning permission on this site expired in May 2019. The scheme has been operating for about 12 years. That works out at 2.3 MW per turbine on average.