Nissan Motors Plant Extn

3 turbines · operational · Tyne and Wear

Wind farm facts

StatusOperational
County / regionTyne and Wear
Turbines3
Installed capacity2 MW
Turbine capacity0.6 MW
Tip heightnot recorded
Operator (or applicant)TNEI Services Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 Project timeline Application submitted June 2007 Permission granted July 2007 Operational April 2008

From application to operation, this scheme took about 1 year.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3964.

What the register tells us

The application was determined in about 1 month. The scheme has been operating for about 18 years. That works out at 0.67 MW per turbine on average.