Noble Foods

1 turbines · operational · Fife

Wind farm facts

StatusOperational
County / regionFife
Turbines1
Installed capacity1.5 MW
Turbine capacity1.5 MW
Tip height127 m
Operator (or applicant)Wind Direct
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 Project timeline Permission expired November 2010 Application submitted May 2011 Permission granted November 2011 Under construction August 2014 Operational December 2014

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4404.

What the register tells us

The application was determined in about 6 months. Construction to first power took about 4 months. A planning permission on this site expired in November 2010. The scheme has been operating for about 12 years. That works out at 1.5 MW per turbine on average.