North Kyle Energy Project

49 turbines · under construction · Strathclyde

Wind farm facts

StatusUnder Construction
County / regionStrathclyde
Turbines49
Installed capacity205.8 MW
Turbine capacitynot recorded
Tip height149.9 m
Operator (or applicant)Brockwell Energy
Turbine manufacturerVestas
Turbine modelV136-4.5

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Project timeline Application submitted September 2019 Permission granted June 2021 Under construction June 2023 Permission expired December 2027

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6607.

What the register tells us

The application was determined in about 21 months. A planning permission on this site expired in December 2027. That works out at 4.2 MW per turbine on average.