North Steads Wind Farm

9 turbines · operational · Northumberland

Wind farm facts

StatusOperational
County / regionNorthumberland
Turbines9
Installed capacity18.45 MW
Turbine capacity2.05 MW
Tip heightnot recorded
Operator (or applicant)Ventient (formerly Infinis)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted January 2012 Permission granted November 2012 Under construction July 2016 Operational July 2016

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3905.

What the register tells us

The application was determined in about 10 months. Construction to first power took about 0 month. The scheme has been operating for about 10 years. That works out at 2.05 MW per turbine on average.