Wind farm facts

StatusOperational
County / regionHereford and Worcester
Turbines1
Installed capacity1.3 MW
Turbine capacity1.3 MW
Tip heightnot recorded
Operator (or applicant)REsense c/o CO2Sense
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~2038201620182020202220242026today1234
  1. 1Jul 2014 — Application submitted
  2. 2Dec 2014 — Permission granted
  3. 3Jun 2015 — Under construction
  4. 4Sep 2015 — Operational

The register also records a planning permission expiry in Dec 2017, after construction had started: an administrative date with no effect on the wind farm, left off the axis.

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 1 year.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4497.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 3 months. A planning permission on this site expired in December 2017. The scheme has been operating for about 11 years. That works out at 1.3 MW per turbine on average.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.