Norton Fields Farm

1 turbines · operational · Hereford and Worcester

Wind farm facts

StatusOperational
County / regionHereford and Worcester
Turbines1
Installed capacity1.3 MW
Turbine capacity1.3 MW
Tip heightnot recorded
Operator (or applicant)REsense c/o CO2Sense
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2013 2014 2015 2016 2017 2018 Project timeline Application submitted July 2014 Permission granted December 2014 Under construction June 2015 Operational September 2015 Permission expired December 2017

From application to operation, this scheme took about 1 year.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4497.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 3 months. A planning permission on this site expired in December 2017. The scheme has been operating for about 11 years. That works out at 1.3 MW per turbine on average.