Nutberry Wind Farm

6 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines6
Installed capacity15 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Renantis Falck Renewables Limited
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted September 2006 Refused September 2008 Permission granted April 2011 Granted on appeal April 2011 Under construction December 2011 Operational September 2013

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3676.

What the register tells us

The application was determined in about 55 months. Construction to first power took about 21 months. The register records a refusal in September 2008 before the scheme progressed. Permission was ultimately granted on appeal in April 2011. The scheme has been operating for about 13 years. That works out at 2.5 MW per turbine on average.