Recorded in WhichWindTurbine: 2 wind turbines. Point the app at one of them to see its profile in real time.
📍 2 turbines mapped — each dot is a turbine recorded in the database. Average position: 53.89641 N · 2.85046 W.
2 turbines · revised · Lancashire
| Status | Revised |
|---|---|
| County / region | Lancashire |
| Turbines | 2 |
| Installed capacity | 4 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Cornwall Light and Power |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
DevelopmentConstructionOperationAhead (repowering horizon at 22 years)
The register links a second scheme on this site (REPD ref 3703, Operational): 2 turbines · 2 MW each · applicant Renewable Energy Generation. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3979.
The application was determined in about 33 months. The register records a refusal in May 2008 before the scheme progressed. Permission was ultimately granted on appeal in December 2010. That works out at 2 MW per turbine on average.
See all wind farms in Lancashire.
| Data | Source | Extract |
|---|---|---|
| Site, capacity, status, planning milestones | Renewable Energy Planning Database (DESNZ, Open Government Licence v3) | Q2 2026, published 03/08/2026 |
| Turbine positions | OpenStreetMap contributors (ODbL) | 19/08/2026 |
| Manufacturer and model | OpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong. | 19/08/2026 |
Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.