Out Newton Wind Farm

7 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines7
Installed capacity9 MW
Turbine capacity1.3 MW
Tip heightnot recorded
Operator (or applicant)Powergen Renewables Developments Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1997 1999 2001 2003 2005 2007 2009 2011 2013 2015 2017 2019 Project timeline Application submitted November 1998 Permission granted September 2000 Operational January 2002 Permission expired September 2019

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2659.

What the register tells us

The application was determined in about 22 months. A planning permission on this site expired in September 2019. The scheme has been operating for about 24 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 1.29 MW per turbine on average.