Owenreagh Wind Farm

10 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines10
Installed capacity5 MW
Turbine capacity0.5 MW
Tip heightnot recorded
Operator (or applicant)EF Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 Scheme REPD 3118 Application submitted October 1995 Permission granted April 1996 Operational January 1997 Permission expired April 2010 Scheme REPD 2927 Application submitted January 2004 Permission granted October 2005 Operational August 2008 Permission expired October 2015

From application to operation, this scheme took about 2 years.

The register links a second scheme on this site (REPD ref 2927, Operational): 6 turbines · 0.85 MW each · applicant EF Energy. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3118.

What the register tells us

The application was determined in about 6 months. A planning permission on this site expired in April 2010. The scheme has been operating for about 29 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.5 MW per turbine on average.