Pant y wal extension

10 turbines · operational · Mid Glamorgan

Wind farm facts

StatusOperational
County / regionMid Glamorgan
Turbines10
Installed capacity25 MW
Turbine capacity2.5 MW
Tip height115 m
Operator (or applicant)Pennant Wind Energy Ventures (PWEV)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Scheme REPD 4039 Application submitted March 2006 Refused April 2006 Permission granted May 2011 Granted on appeal May 2011 Under construction April 2012 Operational June 2013 Permission expired May 2016 Scheme REPD 4409 Application submitted April 2014 Permission granted April 2015 Under construction March 2016 Operational May 2017

From application to operation, this scheme took about 7 years.

The register links a second scheme on this site (REPD ref 4409, Operational): 8 turbines · 2.5 MW each · 125 m tip height · applicant Pennant Walters (PYWX). Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4039.

What the register tells us

The application was determined in about 62 months. Construction to first power took about 14 months. The register records a refusal in April 2006 before the scheme progressed. Permission was ultimately granted on appeal in May 2011. A planning permission on this site expired in May 2016. The scheme has been operating for about 13 years. That works out at 2.5 MW per turbine on average.