🌬️ Onshore wind farm

Pant y wal extension
Mid Glamorgan

Recorded in WhichWindTurbine: 10 wind turbines in operation. Point the app at one of them to see its profile in real time.

10
turbines
25 MW
MW total
2.5 MW
per turbine
115 m
tip height

📍 8 turbines mapped — each dot is a turbine recorded in the database. Average position: 51.61479 N · 3.51164 W.

Pant y wal extension

10 turbines · operational · Mid Glamorgan

Wind farm facts

StatusOperational
County / regionMid Glamorgan
Turbines10
Installed capacity25 MW
Turbine capacity2.5 MW
Tip height115 m
Operator (or applicant)Pennant Wind Energy Ventures (PWEV)
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~20392014201620182020202220242026today1234
  1. 1Apr 2014 — Application submitted
  2. 2Apr 2015 — Permission granted
  3. 3Mar 2016 — Under construction
  4. 4May 2017 — Operational

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 7 years.

The register links a second scheme on this site (REPD ref 4409, Operational): 8 turbines · 2.5 MW each · 125 m tip height · applicant Pennant Walters (PYWX). Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4039.

What the register tells us

The application was determined in about 62 months. Construction to first power took about 14 months. The register records a refusal in April 2006 before the scheme progressed. Permission was ultimately granted on appeal in May 2011. A planning permission on this site expired in May 2016. The scheme has been operating for about 13 years. That works out at 2.5 MW per turbine on average.

Nearby

See all wind farms in Mid Glamorgan.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.