Parc Stormy, Stormy Down

1 turbines · operational · Mid Glamorgan

Wind farm facts

StatusOperational
County / regionMid Glamorgan
Turbines1
Installed capacity2.5 MW
Turbine capacity2.5 MW
Tip height125 m
Operator (or applicant)Cenin Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2013 2014 2015 2016 2017 2018 2019 2020 Project timeline Permission expired August 2014 Application submitted January 2016 Permission granted August 2016 Under construction November 2019

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6013.

What the register tells us

The application was determined in about 7 months. A planning permission on this site expired in August 2014. That works out at 2.5 MW per turbine on average.

Nearby

See all wind farms in Mid Glamorgan.