Park Spring Wind Farm

3 turbines · operational · South Yorkshire

Wind farm facts

StatusOperational
County / regionSouth Yorkshire
Turbines3
Installed capacity8.6 MW
Turbine capacity2.85 MW
Tip heightnot recorded
Operator (or applicant)EDF Energy Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2012 2013 2014 2015 2016 Project timeline Application submitted October 2013 Permission granted April 2014 Under construction April 2015 Operational November 2015

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4410.

What the register tells us

The application was determined in about 6 months. Construction to first power took about 7 months. The scheme has been operating for about 11 years. That works out at 2.87 MW per turbine on average.