6 turbines · operational · Lothian
| Status | Operational |
|---|---|
| County / region | Lothian |
| Turbines | 6 |
| Installed capacity | 19.2 MW |
| Turbine capacity | 3.2 MW |
| Tip height | not recorded |
| Operator (or applicant) | EDF Energy Renewables |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 4 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4211.
The application was determined in about 27 months. Construction to first power took about 15 months. The register records a refusal in June 2013 before the scheme progressed. Permission was ultimately granted on appeal in July 2014. The scheme has been operating for about 10 years. That works out at 3.2 MW per turbine on average.
See all wind farms in Lothian.