Pen Bryn Oer Wind Farm

3 turbines · operational · Mid Glamorgan

Wind farm facts

StatusOperational
County / regionMid Glamorgan
Turbines3
Installed capacity4 MW
Turbine capacity1.33 MW
Tip heightnot recorded
Operator (or applicant)REG Windpower/ BlackRock
Turbine manufacturerVestas
Turbine modelV90

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted June 2013 Refused August 2014 Permission granted August 2015 Granted on appeal August 2015 Under construction January 2017 Operational January 2018 Permission expired August 2018

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4412.

What the register tells us

The application was determined in about 26 months. Construction to first power took about 12 months. The register records a refusal in August 2014 before the scheme progressed. Permission was ultimately granted on appeal in August 2015. A planning permission on this site expired in August 2018. The scheme has been operating for about 8 years. That works out at 1.33 MW per turbine on average.