Penny Hill Lane

6 turbines · operational · South Yorkshire

Wind farm facts

StatusOperational
County / regionSouth Yorkshire
Turbines6
Installed capacity19.8 MW
Turbine capacity3.3 MW
Tip heightnot recorded
Operator (or applicant)Banks Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted July 2009 Permission granted May 2010 Permission expired May 2012 Under construction July 2012 Operational March 2013

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3677.

What the register tells us

The application was determined in about 10 months. Construction to first power took about 8 months. A planning permission on this site expired in May 2012. The scheme has been operating for about 13 years. That works out at 3.3 MW per turbine on average.