Penrhys Wind Farm/Ferndale Power Factory

8 turbines · operational · Mid Glamorgan

Wind farm facts

StatusOperational
County / regionMid Glamorgan
Turbines8
Installed capacity6.4 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)John Laing Environmental Assets Group
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted February 2003 Refused January 2004 Permission granted March 2005 Granted on appeal March 2005 Under construction April 2010 Operational June 2011 Permission expired March 2016

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3660.

What the register tells us

The application was determined in about 25 months. Construction to first power took about 14 months. The register records a refusal in January 2004 before the scheme progressed. Permission was ultimately granted on appeal in March 2005. A planning permission on this site expired in March 2016. The scheme has been operating for about 15 years. That works out at 0.8 MW per turbine on average.