Phase 1 Bettyhill Wind Farm

2 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines2
Installed capacity5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)North British Windpower Ltd
Turbine manufacturerEnercon
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted November 2007 Permission granted August 2011 Operational June 2013

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3380.

What the register tells us

The application was determined in about 45 months. The scheme has been operating for about 13 years. That works out at 2.5 MW per turbine on average.