Pines Burn Wind Farm
Scottish Borders

Recorded in WhichWindTurbine: 7 wind turbines in operation. Point the app at one of them to see its profile in real time.

7
turbines
33.6 MW
MW total
4.8 MW
per turbine
149.9 m
tip height

📍 7 turbines mapped — each dot is a turbine recorded in the database. Average position: 55.34312 N · 2.72582 W.

Pines Burn Wind Farm

7 turbines · operational · Scottish Borders

Wind farm facts

StatusOperational
County / regionScottish Borders
Turbines7
Installed capacity33.6 MW
Turbine capacity4.8 MW
Tip height149.9 m
Operator (or applicant)EnergieKontor UK
Turbine manufacturerNordex
Turbine modelN133/4800
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~204720182020202220242026today1234567
  1. 1Jan 2017 — Application submitted
  2. 2Nov 2017 — Refused
  3. 3Aug 2018 — Permission granted
  4. 4Aug 2018 — Granted on appeal
  5. 5Aug 2021 — Permission expired
  6. 6Jul 2022 — Under construction
  7. 7Oct 2024 — Operational

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6147.

What the register tells us

The application was determined in about 19 months. Construction to first power took about 27 months. The register records a refusal in November 2017 before the scheme progressed. Permission was ultimately granted on appeal in August 2018. A planning permission on this site expired in August 2021. The scheme has been operating for about 2 years. That works out at 4.8 MW per turbine on average.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.