Pogbie Wind Farm 1

6 turbines · operational · Lothian

Wind farm facts

StatusOperational
County / regionLothian
Turbines6
Installed capacity5.1 MW
Turbine capacity0.85 MW
Tip heightnot recorded
Operator (or applicant)Mongoose (formerly Energy Law Unlimited)
Turbine manufacturerVestas
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Project timeline Application submitted September 2008 Permission granted September 2009 Permission expired September 2015 Under construction November 2016 Operational March 2019

From application to operation, this scheme took about 11 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4434.

What the register tells us

The application was determined in about 12 months. Construction to first power took about 28 months. A planning permission on this site expired in September 2015. The scheme has been operating for about 7 years. That works out at 0.85 MW per turbine on average.