🌬️ Onshore wind farm

Pogbie Wind Farm 2
East Lothian

Recorded in WhichWindTurbine: 6 wind turbines in operation. Point the app at one of them to see its profile in real time.

6
turbines
4.8 MW
MW total
0.8 MW
per turbine
74 m
tip height

📍 6 turbines mapped — each dot is a turbine recorded in the database. Average position: 55.82597 N · 2.83149 W.

Pogbie Wind Farm 2

6 turbines · operational · East Lothian

Wind farm facts

StatusOperational
County / regionEast Lothian
Turbines6
Installed capacity4.8 MW
Turbine capacity0.8 MW
Tip height74 m
Operator (or applicant)Mongoose (formerly Energy Law Unlimited/ Pogbie Windfarm)
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~2041201620182020202220242026today1234
  1. 1Aug 2015 — Application submitted
  2. 2May 2016 — Permission granted
  3. 3Jun 2017 — Under construction
  4. 4Mar 2019 — Operational

The register also records a planning permission expiry in May 2019, after construction had started: an administrative date with no effect on the wind farm, left off the axis.

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 5637.

What the register tells us

The application was determined in about 9 months. Construction to first power took about 21 months. A planning permission on this site expired in May 2019. The scheme has been operating for about 7 years. That works out at 0.8 MW per turbine on average.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.