6 turbines · operational · East Lothian
| Status | Operational |
|---|---|
| County / region | East Lothian |
| Turbines | 6 |
| Installed capacity | 4.8 MW |
| Turbine capacity | 0.8 MW |
| Tip height | 74 m |
| Operator (or applicant) | Mongoose (formerly Energy Law Unlimited/ Pogbie Windfarm) |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 4 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 5637.
The application was determined in about 9 months. Construction to first power took about 21 months. A planning permission on this site expired in May 2019. The scheme has been operating for about 7 years. That works out at 0.8 MW per turbine on average.