Pogbie Wind Farm 2

6 turbines · operational · East Lothian

Wind farm facts

StatusOperational
County / regionEast Lothian
Turbines6
Installed capacity4.8 MW
Turbine capacity0.8 MW
Tip height74 m
Operator (or applicant)Mongoose (formerly Energy Law Unlimited/ Pogbie Windfarm)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2014 2015 2016 2017 2018 2019 2020 Project timeline Application submitted August 2015 Permission granted May 2016 Under construction June 2017 Operational March 2019 Permission expired May 2019

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 5637.

What the register tells us

The application was determined in about 9 months. Construction to first power took about 21 months. A planning permission on this site expired in May 2019. The scheme has been operating for about 7 years. That works out at 0.8 MW per turbine on average.