3 turbines · operational · Western Isles
| Status | Operational |
|---|---|
| County / region | Western Isles |
| Turbines | 3 |
| Installed capacity | 9 MW |
| Turbine capacity | 3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Point Power & Energy Ltd / SgurrEnergy |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 7 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4272.
The application was determined in about 44 months. Construction to first power took about 12 months. A planning permission on this site expired in April 2019. The scheme has been operating for about 11 years. That works out at 3 MW per turbine on average.