Potato Pot Wind Farm

3 turbines · operational · Cumbria

Wind farm facts

StatusOperational
County / regionCumbria
Turbines3
Installed capacity6 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Capital Dynamics
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted August 2012 Refused January 2013 Permission granted October 2013 Granted on appeal October 2013 Under construction September 2015 Operational September 2016 Permission expired October 2017

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4233.

What the register tells us

The application was determined in about 14 months. Construction to first power took about 12 months. The register records a refusal in January 2013 before the scheme progressed. Permission was ultimately granted on appeal in October 2013. A planning permission on this site expired in October 2017. The scheme has been operating for about 10 years. That works out at 2 MW per turbine on average.